No description yet. This curated deck is ready for daily study.

Total cards: 8•Content version: v3•Public deck•Updated: 8/1/2026

Card preview (8)

#1
Front (Question)

It is developed by U.S. Navy to handle uncertain activity times, initially for the Polaris missile nuclear submarine project.

Back (Answer)

PERT/Program Evaluation and Review Technique

#2
Front (Question)

It is developed by DuPont & Remington Rand in 1957 for industrial projects for which activity times generally were known.

Back (Answer)

CPM/Critical Path Method

#3
Front (Question)

Have been used to plan, schedule, and control a wide variety of projects.

Back (Answer)

PERT & CPM

#4
Front (Question)

the maximum of the earliest finish times of all activities immediately preceding activity. (O for those with no predecessors)

Back (Answer)

ES/Earliest Start Time

#5
Front (Question)

(Earliest Start Time) + (Time to complete activity)

Back (Answer)

EF/Earliest Finish Time

#6
Front (Question)

the minimum ot the latest start times

Back (Answer)

LS/Latest Finish Time

#7
Front (Question)

(Latest Finish Time - (Time to complete activity)

Back (Answer)

LS/Latest Start Time

#8
Front (Question)

How to calculate slack time?

Back (Answer)

Slack=(LS)-(ES), or =(LF)-(EF)